Diamond Creek Meeting Hall

Contek successfully completed with high quality and in a timely manner all civil and landscaping works required to facilitate the proposed Diamond Creek Meeting Hall. It involved major earthworks with detailed excavation near building foundations.

Main Scope:

• Earthwork 60,000m3
• Batter stabilisation
• Rock lining 2,000m3
• Large rock wall 1,000m3
• Car park with public lighting
• Drainage up to 900mm pipe
• WSUD with two below ground tanks with multiple pump and irrigation systems
• Vicroad intersection upgrades
• LATM's

Client: Cardno
Contract value: $4 million
Completion: 2013