Maryville Way GPT installations

Contek was engaged by Knox City Council to install two CDS Gross Pollutant traps in Maryville Way, Boronia. The traps were installed between a road way and sunken railway easement, with the presence of high pressure gas, high voltage powerlines and a sewer main within the construction zone. With these conditions present, Contek's high level of attention to detail and safety allowed the project to be completed without incident or interruption.
Further, when the location of the above mentioned services conflicted with the design plans, Contek was able to provide a cost effective and functional solution to the clients, whilst maintaining the budget and timeframes.


Main Scope:

• Installation of GPT's and diversion structures up to 7m depth
• Installation of 525mm and 1350mm⌀ pipes, with inverts at 3.7m depth
• Reinstate of the road and surrounds


Client: Knox City Council
Contract value: ~$200 000
Completion: 2015