Golden Grove Creek Bank Remediation Project - Stage 2
Contek Constructions was once again engaged by Knox City Council to remediate and strengthen the creek bank and road which was slowly moving towards the waterway in The Basin. Works involved the demolition and clearing of existing structures, sorting, loading, transporting and placing over 3000t of rocks into an extremely sensitive creek environment, under the watchful eye of some very protective residents. With a tight work zone, requirement to maintain access to residents and a low load limit on the narrow access road, works were sequenced and delivered with both praise from the client and the various stake holders.
Main Scope:
• Careful and selective tree and vegetation removal
• Structural bank reinforcement
• Supply and placement of 3000T of large rocks
• road reinstatement
• Constant resident and stakeholder liaison
Client: Knox City Council
Contract value: $500,000
Completion: 2015